Tailcone primary power system complete

I finished the last remaining items on the tailcone section by connecting the main power wires, starting with the external power port and relays:

Overvoltage crowbar and diode for external power port

Contactors, overvoltage crowbar, and external power port connected

The crowbar requires a circuit breaker (which is actually disengages external power when there's overvoltage), so I placed it on the upper portion of the baggage bulkhead to make sure no baggage would hit it (with a larger hole on the corrugation so it's removable without touching the breaker):

Overvoltage module circuit breaker going through the bulkhead and corrugation

Overvoltage module circuit breaker wired to relay and ground

I had originally planned to have a separate ground cable for each battery, but it quickly became apparent that this would cause trouble at the ground point, so instead I fabricated another copper bar to connect the two batteries:

Grounding point with too many cables coming from the same direction

Batteries with grounds connected by copper bar

I also installed the foam spacers that came with the EarthX batteries, by splitting them in half and attaching them to each side of the battery case (that leaves the side holes open for some ventilation):

Battery cases with spacer foam installed

I'll leave the actual battery installation and securing wires to be part of the avionics section since it also involves connecting the EFII battery wires, Hall Effect sensors, etc. and call this section fully complete.

Time lapse:


Total tailcone rivets: 1904
Total tailcone time: 246.3h

Started installing avionics

The WX-500 Stormscope was by far the hardest LRU to connect cables to - unlike Garmin which just designs to have DB connectors and their backshells hanging from the LRUs, they designed this fancy enclosed box to hold the connectors and provide strain relief to the wires coming into them - that means securing the wires with a clamp inside that box while making sure none of them are under much strain, then closing that all up with the wires coming out of one of the case's holes, which was an exercise in patience (and wire lacing):

WX-500 connectors installed in place

WX-500 connectors with their wires secured inside the case

Closed-up WX-500 case showing the connectors that the LRU attaches to

Closed-up WX-500 case with wires coming out the back

For grounding the GPS antennas, I'm also following recommendations to run wires out of the doublers - and I had added threaded stud inserts to the doublers for that. I'll connect the 3 GPS antenna doublers to the TAS antenna doubler, and that one down to the firewall grounding point. It's not as good as an all-metal cabin top, but it'll still give me only 60mΩ or so (with 18AWG wire).

Measuring ground wires on top of the cabin cover for connecting between each GPS antenna doubler and the TAS antenna doubler 

GPS antenna doublers with grounding wires attached

As provided by SteinAir, the wire bundles were routing the CAN bus all the way to the tailcone to the GTR20, then all the way back to the panel, then to the tailcone again for the pitch and yaw servos - I wanted to shorten that, which would mean redoing at least 4 splices to connect the GTR to the GSA directly. Instead, I did what Garmin says not to do - I added a connector to the CAN bus. Worst case, it won't work and I'll have to take it out and redo those same splices, but this was way simpler and more convenient, and less resistance than the 20-25ft of cable removed from another roundtrip to the panel (according to data sheets, 30mΩ for the Molex SL connector vs 700mΩ for the GF120T-24CANB wire. Capacitance is negligible for CAN frequencies):

GTR20 connector with a CAN bus splice connector for linking to the GSA28s

I also measured and made the top TAS antenna cables (with their fancy QMA connectors) - the run inside the overhead console to the tailcone, and they turn out to be very close to the minimum bend radius when coming out of the antenna, which hopefully won't be an issue:

Top TAS antenna cables terminated on one end

TAS antenna cables terminated and connected to the GTS

Top TAS antenna cables going to antenna through the overhead console

Top TAS antenna attached to tentative ground plane atop the cabin cover

With that, I ran the GTS800 self test (by grounding pin P8002-74), and, to my own surprise, no errors showed up in the assert log! I still want to re-run this test once it's connected to the G3X, but this is very promising.

GTS install tool after self test (pressure altitude fault is expected since it's not yet connected to the GTN)

I also took the opportunity to start attaching panel components:

Some LRUs (GDL51R, fuse block, GAD29, GEA24, VP-X) attached to subpanel in the airplane

We then started running the tailcone wires through the conduits to the panel, starting with the GTS800, WX-500, GTR20 and GSA28s, and then the EFII power wires which connect directly to the batteries:

Tailcone wires going through conduits to the front

Tailcone wires exiting the right-side conduits in the front

EFII power wires exiting the left-side conduit near the panel

Next I need to actually carve the TAS ground plane opening on the cabin cover, attach those antenna doublers in place (which will be a pain to do inside the overhead console), and start final wiring of the panel. I'm waiting for the nose gear to be back on so I can safely climb inside to do wiring.

Time lapse:


Total avionics rivets: 161
Total avionics time: 152.1h

Panel structure riveted in place

As a last step before attaching the panel, we installed some Clickbond fasteners to run cables forward:

Sanding subpanel for Clickbond attachment

Clickbonds behind the subpanel to hold wires that pass to the back

Clickbonds behind subpanel

We then clecoed and riveted the panel in place:

Panel clecoed in place. Standard-size (well, on the short side) wife for reference.

Panel firewall rivets in place

Panel side rivets in place

With this, we were able to continue insulating the firewall.

Time lapse:


Total upper forward fuselage installation rivets: 153
Total upper forward fuselage installation time: 26.7h

Cabin brake hoses installed

Once the oil cooler box was riveted, we installed the brake hoses, starting with the ones near the corner (harder to get to):

First brake hoses attached to parking brake and ALIR

then the ones that connect the pedals:

All brake hoses installed in place

Top view of the brake hoses, showing that they don't touch

Finding the right clocking and direction for all of those to avoid contact took some trial and error - partly because I installed the ALIR a bit further forward than Aircraft Specialty suggested (to have easy access to all the ALIR ports), but also I didn't really want to have all the hoses coming out the center of the pedals 'cause they'd be hitting one another when they moved.

With this, the only steps left on this section are attaching the brake fluid reservoir and filling up the system with brake fluid.

Time lapse:


Total rudder pedals and brake system rivets: 8
Total rudder pedals and brake system time: 22.8h

Oil cooler box riveted

Before final attachment of the engine mount or brake hoses, but after insulating the bottom of the firewall, we riveted the oil cooler box and insulated it:

Oil cooler box riveted to the firewall through the titanium foil

This was a small step to resolve a dependency chain where we wanted those rivets done before installing hte brake hoses, which in turn was much easier to get done before riveting the panel, which in turn had to be done before insulating the top of the firewall.

Once all insulation is done, we'll actually reattach the engine mount and hang the engine for good.

Time lapse:


Total engine installation rivets: 63
Total engine installation time: 14.4h

Avionics attachment progress

We riveted the firewall doublers to the firewall for attaching the sensors:

Firewall doublers riveted in place

Firewall, showing flush doubler rivets

With that, the bottom part of the firewall is ready to insulate (which will be the topic of a separate post, on section 46).

Meanwhile, I also match-drilled the new laser-cut/anodized O2 distributor flat back covers I had made (which, unlike the standard ones, will give me cabin cover clearance, without needing custom-length spacers), and attached them to the aft overhead panel - that made the distributors stick out the bottom just the right amount that the rubber band sealed them up for a nice finish:

New O2 distributor backing plates clamped to the original for match-drilling

Aft overhead console insert with lights and O2 distributors

Top side of the aft overhead console insert with new O2 distributor backing plates

I then match-drilled the tailcone antenna holes (COM, Stormscope) from the doublers/drilling jigs, and attached the tailcone antennas:

Top COM antenna (left), Stormscope antenna (center) and ELT antenna (right), installed in place

Connection to Stormscope antenna

Bottom COM antenna installed in place

Transponder antenna installed in place

In the tailcone, I also attached the autopilot servos:

Pitch and yaw servos attached in the tailcone

and the avionics shelf and the LRUs that go there, including terminating the GTS800 cables (with those annoying QMA connectors):

Avionics shelf attached in the tailcone

GTR20 (left), WX-500 stormscope (center) and GTS800 TAS (right) installed in tailcone, with TAS bottom cables terminated and attached

(for reference, if anyone chooses a similar antenna/GTS position than I did, the total cable lengths was around 7.6ft)

For routing the Stormscope cables, the autpilot servo cables, and the transponder antenna cable, we attached some Clickbond fasteners just below the shelf (conveniently using the lightening hole on the shelf for one of them, and avoiding the GTS attachment nutplates):

Tailcone avionics shelf with Clickbond fasteners underneath it

We then started working on the GPS/XM antennas, that go inside the overhead console (extra annoying to position doublers):

GPS antennas sitting in place on the cabin cover

All top antennas - GPS (x3), COM, Stormscope and ELT

I started preparing the wire bundles to run from the tailcone forward, starting by de-pinning the forward side of all of them, and reducing the sleeving to be just about the length that takes them into the conduit, then splitting the WX-500 wires from the GTR20 wires (for some reason SteinAir put them in the same bundle, at a random distance which doesn't match my layout):

Single bundle with GTR20 and WX-500 cables made by SteinAir

GTR20 and WX-500 wire bundles after splitting them

Still in the tailcone, I made the GTR20 antenna cable (from a leftover 4ft piece of coax):

Trimmed-back coax cable and connector ready for crimping

GTR20 connected to its antenna

Once the panel was riveted in place, we also started installing components there, like the AFR and alternator regulators:

Spartan3 AFR sensor controller installed in place

Alternator regulators installed in place

Still lots left to do in avionics - next is actually running all wires between the tailcone and panel.

Time lapse:


Total avionics rivets: 161
Total avionics time: 140.1h