Mid-fuselage ribs riveting done, skins started

We finished riveting fuselage bulkhead and baggage ribs:

All mid-fuselage ribs and bulkhead riveted in place

I clecoed the bottom skins on and final-drilled all the holes:

Mid-fuselage section with skins on
The floor stiffeners required some fluting to line up properly, then they were final-drilled as well:


Floor stiffeners, fluted and final-drilled in place

Mid-fuselage section with skins and floor stiffeners only (it barely clears the ceiling!)
I found that the holes from the skin to the outboard seat ribs don't align :( so I'll need to flute that part, which will be especially tricky with it already riveted in place:


Since I only have a vise-grip-style fluting plier, which would be even harder to use in this space, I've ordered a regular plier from Spruce and will give that a try when it gets here - I have plenty of other holes and edges to deburr in the meantime.

Time lapse:


Total mid-fuselage ribs and bottom skins rivets: 412
Total mid-fuselage ribs and bottom skins time: 67.5h

Mid-fuselage ribs riveting, part 2

With the parts all primed, I started by riveting various small parts to the ribs:

Step mounting brackets and seat rib subassemblies riveted together
Of course, while doing this, I realized that two little parts had been forgotten when doing primer :( so one more primer session had to be done:

Two seat belt attach lugs I forgot to prime :(
I got lazy this time and decided to do it with rattle-can primer. The color difference doesn't really matter since any apparent parts of the interior will be painted anyway:

Rattle-can-primed seat belt attach lugs, riveted to the rib
I also inserted the heat tee, which allows me to continue riveting the ribs:

Rear tunnel with heat tee installed
I riveted some of those ribs so far:

Most rear seat ribs have been riveted in place

Time lapse:



Total mid-fuselage ribs and bottom skins rivets: 326
Total mid-fuselage ribs and bottom skins time: 55.2h

Firewall riveting

I dimpled then started riveting the firewall parts by the forward seat ribs (aka tunnel), adding all the nutplates, the inspection panel backing plate, the fuel valve attack bracket flanges, and the scat tube support:

Inspection panel backing plate/cover, fuel valve flanges and scat tube support with nutplates riveted

Forward fuselage ribs with nutplates, inspection panel backing plate, nose gear tension fittings and fuel valve bracket flanges riveted on

Forward fuselage rib riveted to nose gear tension fitting

I then dimpled the recess box and the firewall bulkhead to accept the rivets:

Dimpled firewall bulkhead
and finally started riveting it all together:

Firewall bulkhead with most parts riveted to it

Forward side of the firewall bulkhead, with most parts riveted to it

In the process, I also realized that the rivet gauges I have don't match Van's spec - Van's allows smaller shop heads overall, and with some of the rivet lengths they specified, it's impossible to get to the gauge's "official" spec. This applies to most firewall bulkhead rivets, so I had to measure those with a caliper - specifically, the gauge has a hole that's about .19", and the spec calls for .163". The height was almost right on the gauge - the gauge has .06", and the spec is .05".

"Standard" rivet gauges don't really match the MIL-spec that Van's recommends

There's still quite a bit of riveting left to do, but this is a good start.

Time lapse:


Total firewall rivets: 512
Total firewall time: 49.9h